Pipe Schedule Chart (Sch 40 & Sch 80)

Updated 2026-11-08 · Screening reference — confirm against the current ASME / API / EN edition before IFC.

Direct answer · Pipe schedule chart

A pipe schedule chart gives wall thickness for a given NPS. Sch 40 is the common standard-weight wall; Sch 80 is thicker for higher pressure/erosion. Valve bore and end prep must match the pipe schedule on buttweld ends.

Need valves matching this chart? Send size · rating · MOC · ends · qty.

Contact / RFQ WhatsApp

Carbon steel — OD & wall (mm)

NPSDNOD (mm)Sch 40 wall (mm)Sch 80 wall (mm)
½"1521.32.773.73
¾"2026.72.873.91
1"2533.43.384.55
1½"4048.33.685.08
2"5060.33.915.54
3"8088.95.497.62
4"100114.36.028.56
6"150168.37.1110.97
8"200219.18.1812.70
10"250273.19.2712.70
12"300323.99.5312.70
14"350355.69.5312.70
16"400406.49.5312.70
18"450457.29.5312.70
20"500508.09.5312.70
24"600610.09.5314.27

Stainless schedules (e.g. Sch 10S/40S) differ — do not mix carbon and stainless schedule tables. ID = OD − 2×wall (approx).

Why valve buyers care

Buttweld valves are ordered to match pipe schedule (e.g. BW Sch 40). Flanged valves care more about flange class than schedule, but branch velocity and Cv sizing still use ID from the schedule chart.

End typeSchedule note on RFQ
Flanged RF/RTJSchedule optional unless bore match required
Buttweld (BW)Mandatory — Sch 40 / 80 / XS / XXS
Socket weld / NPTUsually ≤2"; schedule still affects coupling

FAQ

Is Sch 40 the same as standard wall?

For many NPS sizes historically yes, but always use the numeric schedule wall from B36.10 for design.

Does higher schedule mean higher flange class?

No. Schedule is pipe wall; Class/PN is flange/valve rating. Both must be specified.

Where is the older pipe schedule table?

See also pipe-schedule-table.html in this folder for the interactive/legacy view.